Development projects currently progressing through regulatory approval are:
Modification 10: Increase to mine footprint and mine life
Description
An additional 85 hectares (ha) of disturbance outside mine disturbance boundary and inside project approval boundary.
Recovery of an additional 30 Million tonnes (Mt) of Run of Mine (ROM) coal.
An additional four years of mining activities out to the end of 2040.
Current status of environmental approval pathway
A Scoping Request was submitted to NSW Department of Planning, Housing and Infrastructure.
Modification 10 was lodged in May 2025 with Public Exhibition in June/July 2025.
The application is currently in the final assessment phase.
Consultation
A Stakeholder Consultation Strategy for each development project is developed with the identification of key regulatory and community stakeholders, along with the development of stakeholder engagement plans.
Community engagement has primarily taken the form of regular Newsletter updates to neighbours, discussions with affected stakeholders who request a briefing, and regular presentations to the Community Consultative Committee (CCC). Presentations and other materials related to CCC meetings can be found at: Boggabri Coal Community Consultative Committee.
The main purpose of the Stakeholder Consultation Strategy is to identify any community concerns so they can be carefully considered in the planning and approvals process.
Contact Details
For questions regarding the Modification please contact:
Boggabri Coal Environmental Compliance Superintendent
Phone: 1800 264 422 74
or by submitting an enquiry via link: Contact us.